国产热热热精品,亚洲视频久久】日韩,三级婷婷在线久久,99人妻精品视频,精品九热人人肉肉在线,AV东京热一区二区,91po在线视频观看,久久激情宗合,青青草黄色手机视频

USEUROPEAFRICAASIA 中文雙語Fran?ais
China
Home / China / Business

State Grid Corp asks Brazil to speed up power line approval

By Reuters | China Daily | Updated: 2017-01-05 07:44

State Grid Corp of China has asked the Brazilian government and regulators to speed up environmental licensing of a planned power line connecting to the Belo Monte dam in the Amazon forest, according to official documents and a source with direct knowledge of the matter.

State Grid, the world's biggest utility, fears it could have to delay construction of the line, possibly forcing the third-largest hydroelectric power dam to begin operating in 2019 below full capacity.

Belo Monte, a dam built on the Xingu River in the Amazon forest, will have a total installed capacity of 11,233 megawatts, exceeded only by China's Three Gorges and Brazil's Itaipu dams.

The Chinese firm, together with two units of the Centrais El??tricas do Brasil SA state-controlled utility, has begun work in the first of two transmission lines linking Belo Monte to cities throughout Brazil.

The source said State Grid had expected to receive a preliminary license from Brazil's Ibama environmental agency for a second 2,500 kilometers-long transmission line by October 2016 and authorization to begin construction by February 2017.

Ibama has not issued either of the licenses for the second transmission line, which will carry power to the southeast, Brazil's biggest energy consumer, and other states.

The source said that while the delay did not affect the construction schedule, the preliminary authorization needs to be issued in January, followed by the building authorization in March.

Ibama said its analysis was still underway and it had no estimate of when it would be completed.

Last week, Brazil's power regulator Aneel contacted the Energy and Mining Ministry to ask for support in speeding up the licensing process, an Aneel document seen by Reuters showed.

Construction of the power line, which State Grid estimates will cost 7 billion reais ($2.15 billion), needs to be completed by December 2019 if Belo Monte is to operate in full capacity.

A State Grid document seen by Reuters said that delays in the licensing process would also force it to disburse additional money as it could miss deadlines for receiving funds from state development bank BNDES.

 

Editor's picks
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
呼伦贝尔市| 揭西县| 宁晋县| 昌平区| 拉萨市| 广元市| 桐柏县| 肃宁县| 镇远县| 文成县| 温宿县| 邵阳市| 阿克| 扶沟县| 汾西县| 西充县| 全南县| 周至县| 怀宁县| 雷波县| 敖汉旗| 麻城市| 中卫市| 磐安县| 桂平市| 玉屏| 慈溪市| 封开县| 泾川县| 巴彦县| 凤凰县| 达尔| 诸暨市| 隆安县| 铜川市| 沈阳市| 石首市| 绥阳县| 乌鲁木齐县| 西丰县| 晋江市|